Most kitchen projects don't fail in construction — they fail in planning. Here is the framework we walk every client through before a single drawing is started.
Step 1 — Honest budget
Pick a target budget, then add 15% for contingency before you've signed anyone. If that number isn't comfortable, simplify scope before you fall in love with finishes.
Step 2 — Decide if you need an architect
Walls moving, ceilings changing, windows added, or the kitchen relocating — yes, architect. Finishes-only on the same footprint — designer plus contractor is enough.
Step 3 — Lead times decide the calendar
- ·Premium domestic cabinetry: 8–10 weeks
- ·Imported European cabinetry: 16–22 weeks
- ·Sub-Zero / Wolf appliances: 8–14 weeks
- ·Specialty stone fabrication: 4–6 weeks after template
Step 4 — Permits and inspections
In most MA towns plan 4–8 weeks for permitting on anything structural. Electrical and plumbing inspections add days, not weeks, if scheduled in advance.
Step 5 — Sequence the trades
Demo, rough plumbing, rough electrical, framing changes, drywall, floors, cabinets, stone template, stone install, appliances, lighting trim, paint touch-up. Skipping or reordering steps adds weeks, not days.
The single biggest planning mistake
Ordering cabinetry before the architect's drawings are stamped. Every change after order is a credit memo and a delay.
Interactive · estimator
Plan your project
Use our estimator to anchor budget and scope before you call a single contractor.
Open estimatorFAQ
Frequently asked questions
Plan for 6–10 months total: 3–5 months of design and procurement, 6–10 weeks of construction, and 2–4 weeks of punch list and touch-up.
Next step
